All POs issued · Vitro lamination at 65% · Crane scheduled May 18-19 · Hospital wing closure confirmed
Site Logistics — Hospital Specific
Work hours6:00 PM – 2:00 AM
Wing closurePavilion A 4N · Confirmed
Patient relocationN/A · lobby only
Loading dockDock 3 · badge entry
ICRA ClassIII
Negative pressureRequired
Daily clearanceATP < 30 RLU
Crane swingRose St lane closure 6p-8p
Hospital protocol: All crew badged through UK Security · Containment walls go up before any glass demo · Daily debrief with FM Contact (Sandra Mullins) at 5:30 PM start
Activity
🚚
Allied CraneApr 26, 9:14 AM
Crane confirmed for May 18-19 · lift plan filed
📦
VitroApr 24, 11:00 AM
PO-0301 production update: 65% complete · on track for May 14
📋
UK FM (Sandra Mullins)Apr 22, 3:18 PM
Wing closure approved by hospital ops · Pavilion A 4N May 17-22
Sherman Carter BarnhartApr 17, 4:48 PM
All 5 submittals approved · including ICRA plan
📄
Doc HollidayApr 14, 10:00 AM
Issued PO-0301 (Vitro) and PO-0302 (Anchor-Ventana)
📝
UK HealthCareMar 27, 2:00 PM
Signed PO UKM-2026-CW-0214 · 25% deposit $10,700
📅
SystemMar 19, 11:00 AM
Job created from EST-2026-0411