Stage
🚚
All POs issued · Vitro lamination at 65% · Crane scheduled May 18-19 · Hospital wing closure confirmed
Submittals — Approved (Healthcare)
Architect-signed Lobby Renderings
SUB-01 · Sherman Carter Barnhart · 6 sheets stamped Mar 28
ASHRAE 90.1 Energy Compliance
SUB-02 · Thermal calcs · U-factor 0.34 · SHGC 0.27
Hospital Infection Control Plan (ICRA Class III)
SUB-03 · Containment, HEPA negative pressure, daily clearance
Glass Spec — Vitro Solarban 60 Laminated
SUB-04 · 1/4" laminated low-iron · ASTM E2190 / E2353
Crane Lift Plan & Anchor Calcs
SUB-05 · EOR-stamped · Allied Crane · Rose St lane closure plan
Takeoff — Curtain Wall (12 panels)
| # | Panel | W × H (ft) | Glass | Anchor | Qty | Unit Wt (lbs) | Total |
|---|---|---|---|---|---|---|---|
| CW1-CW4 | East lobby field, row 1 | 5'-0" × 9'-6" | 1/4" lam low-iron + interlayer | Halfen anchor + structural sealant | 4 | 285 | 1,140 |
| CW5-CW8 | East lobby field, row 2 | 5'-0" × 9'-6" | 1/4" lam low-iron + interlayer | Halfen anchor + structural sealant | 4 | 285 | 1,140 |
| CW9-CW10 | Corner panels (mitered) | 3'-6" × 9'-6" | 1/4" lam low-iron, mitered edge | Halfen + L-bracket | 2 | 200 | 400 |
| CW11-CW12 | Spandrel infill panels | 5'-0" × 3'-6" | 1/4" lam, opaque ceramic frit | Halfen anchor | 2 | 105 | 210 |
| TOTALS | 12 panels | — | 2,890 lbs | ||||
Sq Ft
505
Total Wt
2,890 lbs
Heaviest
285 lbs
Crane pick
2-panel
Purchase Orders (4) & Vendor Lead Times
PO-2026-0301
Vitro Architectural Glass
$14,200
In Production
Solarban 60 lam low-iron, 12 lites + 2 spandrel ceramic frit$13,400
Custom interlayer (acoustic dampening)$540
Freight (LTL flatbed, padded)$260
PO-2026-0302
Anchor-Ventana Glass
$3,900
Acknowledged
Lamination — 12 panels + 2 spandrel$3,360
Edge polishing + miter (CW9, CW10)$420
Heat-soak test (ASTM C1376)$120
PO-2026-0303
Allied Crane & Rigging
$3,600
Confirmed
40-ton hydraulic crane — $1,800/day x 2 days$3,600
PO-2026-0305
CleanSpace — ICRA Containment
$480
Scheduled
Negative-pressure containment walls + HEPA — 5 days$380
Daily ATP swab clearance$100
4 POs · Material + crane + containment
$22,180
Site Logistics — Hospital Specific
Work hours6:00 PM – 2:00 AM
Wing closurePavilion A 4N · Confirmed
Patient relocationN/A · lobby only
Loading dockDock 3 · badge entry
ICRA ClassIII
Negative pressureRequired
Daily clearanceATP < 30 RLU
Crane swingRose St lane closure 6p-8p
Hospital protocol: All crew badged through UK Security · Containment walls go up before any glass demo · Daily debrief with FM Contact (Sandra Mullins) at 5:30 PM start
Activity
🚚
Allied CraneApr 26, 9:14 AM
Crane confirmed for May 18-19 · lift plan filed
📦
VitroApr 24, 11:00 AM
PO-0301 production update: 65% complete · on track for May 14
📋
UK FM (Sandra Mullins)Apr 22, 3:18 PM
Wing closure approved by hospital ops · Pavilion A 4N May 17-22
✅
Sherman Carter BarnhartApr 17, 4:48 PM
All 5 submittals approved · including ICRA plan
📄
Doc HollidayApr 14, 10:00 AM
Issued PO-0301 (Vitro) and PO-0302 (Anchor-Ventana)
📝
UK HealthCareMar 27, 2:00 PM
Signed PO UKM-2026-CW-0214 · 25% deposit $10,700
📅
SystemMar 19, 11:00 AM
Job created from EST-2026-0411