Stage
✅
Submittals approved Apr 18 · Permit #2026-CE-04-0142 issued Apr 22 · Materials shipping May 11 · Install starts May 12
Submittals — Approved
Glass Specification — Vitro Solarban 70 LowE
SUB-01 · Vitro data sheet + thermal performance · ASTM C1036 / C1048
Shop Drawings v3 — East Elevation
SUB-02 · 4 sheets · Stamped by architect · rev3 Apr 16
Hardware Cut Sheets — CRL JE Series
SUB-03 · Entrance hardware + push/pulls · ANSI/BHMA A156.16
Tempering Compliance — Anchor-Ventana
SUB-04 · ASTM C1376 heat-soak test cert · CPSC 16 CFR 1201
Anchor & Sealant Schedule
SUB-05 · Dow 795 structural silicone · Anchor calcs by EOR
All 5 submittals stamped APPROVED by Lord Aeck Sargent · Apr 18, 2026 · No re-submittals required
Takeoff — Glass & Hardware
| # | Element | W × H (ft) | Glass | Edge | Hardware | Qty | Unit Wt (lbs) | Total Wt |
|---|---|---|---|---|---|---|---|---|
| P1 | Storefront panel L1 | 5'-0" × 14'-0" | 1/2" tempered Solarban 70 | All polished | Top/bottom rails | 1 | 434 | 434 |
| P2 | Storefront panel L2 | 5'-0" × 14'-0" | 1/2" tempered Solarban 70 | All polished | Top/bottom rails | 1 | 434 | 434 |
| P3 | Door jamb panel L | 3'-6" × 14'-0" | 1/2" tempered Solarban 70 | Polished, hinge prep | JE pivot prep | 1 | 304 | 304 |
| D1 | Entrance door | 3'-0" × 7'-0" | 1/2" tempered low-iron | Polished | CRL JE pivot + push/pull | 1 | 130 | 130 |
| D2 | Door transom | 3'-0" × 7'-0" | 1/2" tempered Solarban 70 | Polished | Header anchored | 1 | 130 | 130 |
| P4 | Door jamb panel R | 3'-6" × 14'-0" | 1/2" tempered Solarban 70 | Polished, hinge prep | JE pivot prep | 1 | 304 | 304 |
| P5 | Storefront panel R1 | 5'-0" × 14'-0" | 1/2" tempered Solarban 70 | All polished | Top/bottom rails | 1 | 434 | 434 |
| P6 | Storefront panel R2 | 5'-0" × 14'-0" | 1/2" tempered Solarban 70 | All polished | Top/bottom rails | 1 | 434 | 434 |
| TOTALS | 8 lites | — | 2,604 lbs | |||||
Sq Ft
441
Total Weight
2,604 lbs
Heaviest
434 lbs
Purchase Orders (4)
PO-2026-0287
Vitro Architectural Glass
$8,420
Acknowledged
Solarban 70 LowE 1/2" lites — 6 ea (per shop drawings)$7,860
Door + transom lites 1/2" low-iron — 2 ea$420
Freight (LTL flatbed)$140
PO-2026-0288
Anchor-Ventana Glass
$2,180
Shipped
Tempering + heat-soak test, 8 lites (ASTM C1376)$1,840
Edge polishing — 6 storefront panels$240
Hinge prep — 2 jamb panels$100
PO-2026-0291
CRL (C.R. Laurence)
$1,840
Issued
JE Series pivot set, brushed aluminum — 1 ea$680
Push/pull bar set 36", BSS — 1 pr$420
Top/bottom rails for storefront panels — 6 ea$540
Setting blocks, anchors, weatherseal kit$200
PO-2026-0294
Sunbelt Rentals — Lift
$1,280
Confirmed
40' boom lift, 4WD — $640/day x 2 days$1,280
4 POs · Material total + lift rental
$13,720
Shop Drawings v3 — Preview
📄
East Elevation — Sales Pavilion
4 sheets · PDF · Stamped Lord Aeck Sargent · rev 3 Apr 16
Site Logistics
AccessVersailles Rd gate, badge required
Lay-downEast lot, 30x60 staging
Crane swingNot needed (lift)
Site contactMark Bezner (GC)
Hours allowed7a-7p, no Sun
Crew & Cert Requirements
60-Glass ForemanVerified
OSHA 10All 4 crew
Aerial liftReynolds + Holliday
Bonded$50K project bond
Safety planFiled Apr 24
Activity
📦
Anchor-VentanaApr 26, 2:14 PM
PO-0288 shipped · tracking RFY-441208 · ETA May 8
📋
LFUCGApr 22, 10:30 AM
Permit #2026-CE-04-0142 issued · valid 6 months
📦
CRLApr 21, 4:02 PM
PO-0291 received · production scheduled
✅
Lord Aeck SargentApr 18, 3:48 PM
All 5 submittals stamped APPROVED
📄
Doc HollidayApr 16, 11:20 AM
Submittal package v3 sent to architect (5 docs)
📝
Keeneland AssociationApr 8, 1:00 PM
Signed estimate · PO KA-2026-PO-0079 · 30% deposit $8,520
📅
SystemApr 4, 9:00 AM
Job created from EST-2026-0464